Steps in Building

Blockwork


Framing

     This method of steel-reinforced concrete construction will meet or exceed anyone's definition of superior construction. It's durable, low maintenance, energy efficient, quiet, comfortable, sturdy and long
lasting.

 During this stage of building everything seems to go very quickly - it is important to be organized and know when each trade is required and what they might need to complete their job.

The commonest building unit in The Gambia is the sand-cement block. Because it is cheap and easy to make. The blocks are not load bearing and are usaully rendered after construction.

20. Framing: The materials needed for framing should have been manufactured and left for a minimum period of seven days to cure.

  • Order Trusses
  • Once framing starts establish when the Windows and Exterior Doors should be delivered.
  • At this time you should be sure of the layout of your house; discuss any changes with your builder. Alterations later on can be messy, costly, and very frustrating for the building crew. Drop by at the end of the days work. And do not forget that they are there to make a living. Make sure they can do their job by having the materials on site when they are needed.

21. Trusses: When the builder are ready to place the trusses a crane should be on site to lift the trusses to the roof.

NOTE: Too many people working at the same time could create problems. Each trade needs space and time to do a proper job.

22. Plumbing:

Note: It is very important that the Plumbing Trades know where the cabinets are to be installed.

  • A rough in for the air conditioning is good to include.

23. Roofing: Once the Framers are done with the roof it is time for the Roofers to do their work.

24. Electrical: Electricians start with their wiring.

  • Note: It is very important that the Electrician knows where the cabinets are to be installed.
  • Note: Walk through the house with the Electrician and show them where you want all the outlets to be installed.
  • Most Electricians will install the Cable and Telephone wires.

25. Doors & Windows: When the exterior doors and windows are installed, the house can be locked up.

  • Make sure the windows price includes screens and night locks. It is very frustrating when you do not notice that the excellent price you got does not include these items.
  • The Exterior Doors and Windows should be delivered before the Framers are finished with the roof so they won't have to come back for them later.

 

L o c k - u p s t a g e  C o m p l e t e d