This method of
steel-reinforced concrete construction will meet or exceed
anyone's definition of superior construction. It's durable,
low maintenance, energy efficient, quiet, comfortable, sturdy
and long
lasting.
During this stage
of building everything seems to go very quickly - it
is important to be organized and know when each trade is
required and what they might need to complete their job.
The commonest building unit in The Gambia is the sand-cement
block. Because it is cheap and easy to make. The blocks are
not load bearing and are usaully rendered after construction.
20. Framing: The materials needed for
framing should have been manufactured and left for a minimum
period of seven days to cure.
- Order Trusses
- Once framing starts establish when the Windows and
Exterior Doors should be delivered.
- At this time you should be sure of the layout of
your house; discuss any changes with your builder. Alterations
later on can be messy, costly, and very frustrating for
the building crew. Drop by at the end of the days
work. And do not forget that they are there to make a
living. Make sure they can do their job by having the
materials on site when they are needed.
21. Trusses: When the builder are
ready to place the trusses a crane should be on site to lift
the trusses to the roof.
NOTE: Too many people working at the
same time could create problems. Each trade needs space
and time to do a proper job.
22. Plumbing:
Note: It
is very important that the Plumbing Trades
know where the cabinets are to be installed.
- A rough in for the air conditioning is good to include.
23. Roofing: Once the Framers are done
with the roof it is
time for the Roofers to do their work.
24. Electrical: Electricians start with
their wiring.
- Note: It is very
important that the Electrician knows where the cabinets
are to be installed.
- Note: Walk through
the house with the Electrician and show them where you
want all the outlets to be installed.
- Most Electricians will install the Cable and Telephone
wires.
25. Doors & Windows: When the exterior
doors and windows are installed, the house can be locked
up.
- Make sure the windows price includes screens and
night locks. It is very frustrating when you do not notice
that the excellent price you got does not include these
items.
- The Exterior Doors and Windows should be delivered
before the Framers are finished with the roof so they
won't have to come back for them later.
L o c k - u p s t a g e C
o m p l e t e d
|